HEAD OFFICE
Project name
Amazon ARS Fulfilment Centre, Oakdale West Industrial Estate
Client
Amazon with Goodman and delivery partners
Location
Kemps Creek, NSW
Year
2020
Scope of work by Antec
Supply of approximately 610,000 shear studs.
Background
The project is Australia’s first multi-level robotics-enabled fulfilment centre with about 200,000 m² across four levels and capacity for up to 20 million items.
Challenge
Extraordinary volume and accelerated programme required robust procurement, storage planning and continuous delivery flow.
Antec’s solution
High-volume headed shear connectors produced and delivered in phased consignments with complete QA packs.
Implementation
Benefits and results
Key takeaways
Why this project matters for Antec
Showcases Antec’s ability to scale supply for the largest industrial builds in Australia.